Domestic Drainage Method Statement

By: Admin

 

 

        METHOD STATEMENT

 

Project Name: Clients Project name

Project Number:

Work Activity: Drainage

Work Location: 

Date:

Reference Number:

Prepared by:

Approved by:

 

Objective:

Installation, and connection of new 100mm drainage pipes to existing surface and foul manholes

Location:

 

Timescale:

Add Programmed start and end for this phase of works

Welfare and First Aid:

Add details, you must mention toilets and drinking water, First Aiders and First Aid Box

Reducing Risk:

  • Banksman Present during works
  • No un-authorized persons allowed on site during excavations
  • Area Inspected before works commence daily, and at suitable intervals during the day.
  • Excavations fenced off and end of the day.
  • Excavated material to be kept a minimum of 1.5m away from excavation.
  • Warning signs
  • PPE to be worn at all times.

 

           

Health, Safety and Environmental Assessments:

N/A Ground Investigation Clear ( Cable Avoidance Tool used to scan line of pipes, local authority/waterboard and Gas lines checked and marked.

 

Related Assessments:

RA003 Excavations

RA001 Plant

 

Supervision:

Add supervisor

Training:

Add CSCS details

Labour:

Add all Labour for this phase

 

Plant / Equipment:

13 Ton tracked Excavator

3 Ton Forward Tipping Dumper

 

Work Method:

  1. The new drain positions will be set out by competent person.
  2. Cable avoidance tool then used to re-check route.
  3. Levels of existing connection points will be checked, and any level differences against engineers design drawing to be reported.
  4. A trench will be excavated alone the line of the new pipe, level control by pipe laser or manual level.
  5. Pipes will be installed as per the design specification EG concrete surround and backfilling with as dug material.
  6. Testing will be carried out prior to backfilling to ensure pipes are installed correctly and sealed in accordance with manufacturers guidelines in addition water authority may wish to witness tests prior to adoption of system.
  7. New manholes will be constructed where required, and steps will be taken to avoid any disruption of existing flows.

 

 

Emergencies:

A mobile phone will be available at all times to summon emergency services, the site supervision staff will be advised of the nearest hospital. A First aid box, with eyewash liquid will be kept on site.

This method statement will be the subject of a toolbox talk given to all personnel involved with the work activity.

 

 

About the Author:

Admin have been involved with UK Construction safety for many years.


This Article is Brought to you by:

Building and Construction Method Statements and Risk Assessments


 

 

Method Statement Template Related Articles:

Method Statement Installation of domestic central heating system

  ...

By: Admin

How Detailed Should A Method Statement Be? Part 1

How detailed should a method statement be? Part 1 The contents of a method statement should be used as a briefing or "tool box talk" withthe persons that will actually be carrying o...

By: Admin

COSHH - Water Based Emulsion Paint

 The basic assessment below has been performed using...

By: NJG

Updated Health and Safety Related News:

Health and safety gone a ?small bit over the top? - Limerick councillor

WHEN A councillor rang the area?s road department at 11.30pm to respond to a tree blocking a road he was told they couldn?t come out until daybreak, heard a Cappamore/Kilmallock municipal area meeting...


PerkinElmer Named 2014 ?Company of the Year? by Instrument Business Outlook

PerkinElmer, Inc. , a global leader focused on improving the health and safety of people and the environment, today announced that it has been named 2014 ?Company of the


Most sites fail safety checks

THE MAJORITY of construction sites across Worcestershire have failed basic health and safety spot-checks. A total of 14 out of the 23 inspections conducted during a month-long drive by the Health and ...



More Resources: