Domestic Drainage Method Statement

By: Admin





Project Name: Clients Project name

Project Number:

Work Activity: Drainage

Work Location: 


Reference Number:

Prepared by:

Approved by:



Installation, and connection of new 100mm drainage pipes to existing surface and foul manholes




Add Programmed start and end for this phase of works

Welfare and First Aid:

Add details, you must mention toilets and drinking water, First Aiders and First Aid Box

Reducing Risk:

  • Banksman Present during works
  • No un-authorized persons allowed on site during excavations
  • Area Inspected before works commence daily, and at suitable intervals during the day.
  • Excavations fenced off and end of the day.
  • Excavated material to be kept a minimum of 1.5m away from excavation.
  • Warning signs
  • PPE to be worn at all times.



Health, Safety and Environmental Assessments:

N/A Ground Investigation Clear ( Cable Avoidance Tool used to scan line of pipes, local authority/waterboard and Gas lines checked and marked.


Related Assessments:

RA003 Excavations

RA001 Plant



Add supervisor


Add CSCS details


Add all Labour for this phase


Plant / Equipment:

13 Ton tracked Excavator

3 Ton Forward Tipping Dumper


Work Method:

  1. The new drain positions will be set out by competent person.
  2. Cable avoidance tool then used to re-check route.
  3. Levels of existing connection points will be checked, and any level differences against engineers design drawing to be reported.
  4. A trench will be excavated alone the line of the new pipe, level control by pipe laser or manual level.
  5. Pipes will be installed as per the design specification EG concrete surround and backfilling with as dug material.
  6. Testing will be carried out prior to backfilling to ensure pipes are installed correctly and sealed in accordance with manufacturers guidelines in addition water authority may wish to witness tests prior to adoption of system.
  7. New manholes will be constructed where required, and steps will be taken to avoid any disruption of existing flows.




A mobile phone will be available at all times to summon emergency services, the site supervision staff will be advised of the nearest hospital. A First aid box, with eyewash liquid will be kept on site.

This method statement will be the subject of a toolbox talk given to all personnel involved with the work activity.



About the Author:

Admin have been involved with UK Construction safety for many years.

This Article is Brought to you by:

Building and Construction Method Statements and Risk Assessments

Method Statement Template Related Articles:

Method Statement for Ground Investigation- Trial Holes

Method Statement:- Trial Holes...

By: Admin

50 Document Construction Pack

Our popular building and construction pack containing 50 useful method statements, risk assessments and coshh is available for just 49.99 thats just 1.00 each! Please visit our online store to purchase with instant downl...


Method Statement For General Office Cleaning

Method Statement (Safe System of Work) Contract Name: Address: Ref: MS001 Description of Works: (Main objective) General- Cleaning Expected Start and End D...

By: Admin

Updated Risk assessment Related News:

More Resources: