Domestic Drainage Method Statement

By: Admin

 

 

        METHOD STATEMENT

 

Project Name: Clients Project name

Project Number:

Work Activity: Drainage

Work Location: 

Date:

Reference Number:

Prepared by:

Approved by:

 

Objective:

Installation, and connection of new 100mm drainage pipes to existing surface and foul manholes

Location:

 

Timescale:

Add Programmed start and end for this phase of works

Welfare and First Aid:

Add details, you must mention toilets and drinking water, First Aiders and First Aid Box

Reducing Risk:

  • Banksman Present during works
  • No un-authorized persons allowed on site during excavations
  • Area Inspected before works commence daily, and at suitable intervals during the day.
  • Excavations fenced off and end of the day.
  • Excavated material to be kept a minimum of 1.5m away from excavation.
  • Warning signs
  • PPE to be worn at all times.

 

           

Health, Safety and Environmental Assessments:

N/A Ground Investigation Clear ( Cable Avoidance Tool used to scan line of pipes, local authority/waterboard and Gas lines checked and marked.

 

Related Assessments:

RA003 Excavations

RA001 Plant

 

Supervision:

Add supervisor

Training:

Add CSCS details

Labour:

Add all Labour for this phase

 

Plant / Equipment:

13 Ton tracked Excavator

3 Ton Forward Tipping Dumper

 

Work Method:

  1. The new drain positions will be set out by competent person.
  2. Cable avoidance tool then used to re-check route.
  3. Levels of existing connection points will be checked, and any level differences against engineers design drawing to be reported.
  4. A trench will be excavated alone the line of the new pipe, level control by pipe laser or manual level.
  5. Pipes will be installed as per the design specification EG concrete surround and backfilling with as dug material.
  6. Testing will be carried out prior to backfilling to ensure pipes are installed correctly and sealed in accordance with manufacturers guidelines in addition water authority may wish to witness tests prior to adoption of system.
  7. New manholes will be constructed where required, and steps will be taken to avoid any disruption of existing flows.

 

 

Emergencies:

A mobile phone will be available at all times to summon emergency services, the site supervision staff will be advised of the nearest hospital. A First aid box, with eyewash liquid will be kept on site.

This method statement will be the subject of a toolbox talk given to all personnel involved with the work activity.

 

 

About the Author:

Admin have been involved with UK Construction safety for many years.


This Article is Brought to you by:

Building and Construction Method Statements and Risk Assessments


 

 

Method Statement Template Related Articles:

Domestic Drainage Method Statement

  ...

By: Admin

Method Statement Format

...

By: NJG

Breaking down building work into sequences

Breaking Work down into Sequences for method statements ...

By: Admin

Updated Health and Safety Related News:

?2.1m fines for deaths at work last year

Companies flouting health and safety standards have been hit with one of the highest ever total annual fines issued in this country, after 47 deaths occurred in Irish workplaces last year.


Focus on health and safety sharpens

Workplace health and safety is back in the media spotlight after a recent appeal of a major retailer's sentence and the progress through Parliament of new legislation set to line up our regime...


Booming mobile health app market needs more FDA oversight for consumer safety...

While the mobile health apps market offers tremendous potential, several health law experts say that more oversight is needed by the US Food and Drug Administration to ensure consumer confidence and s...



More Resources: